GRANT STREET CONSTRUCTION BEGINS JUNE 1, 2021

  • Interested in serving on a board or commission?

    Submit your questionnaire for consideration.

The City of Macomb Public Works Department announces that the Micro
surfacing project on Grant Street between S. Johnson Street and Candy Lane will begin
June 1, 2021 and is expected to be complete by June 25, 2021. The contractor has
indicated that they will be maintaining 2 lanes of traffic along Grant St. for the entire project.
However, the actual lanes will be moved as they work. Please pay attention to the traffic
control signs to make sure that you are driving in the correct lane. There may be short
periods of time where traffic will not be able to cross Grant St. to turn on to side streets or
driveways. We are encouraging larger vehicles to use other routes if possible.
“We appreciate the patience from the community and visitors as we preserve the road ways
of the City of Macomb,” stated Public Works Director, Alice Ohrtmann. For more
information visit www.cityofmacomb.com or City of Macomb, IL Facebook page.
Questions, please contact Public Works at 309-833-2821.